On July 28, colorful flags fluttered at the site of Unit 1 of the first phase of Huaneng Shandong Shidao Bay Nuclear Power Expansion Project, and construction workers were busy shuttling back and forth. With a command, the Zoomlion concrete pump truck on site poured the first cubic meter of concrete into the nuclear island through the pipeline, marking the official start of the project. This is another breakthrough achieved by the base in the construction of independent third-generation nuclear power "Hualong One" units since the world's first fourth-generation nuclear power plant was put into commercial operation here in December last year.
During this pouring operation, the project party optimized the process and planned for the first time to synchronize the construction with the surrounding plant raft foundation. During the peak period on site, 8 pouring equipment were started at the same time for collaborative operation to ensure the efficiency and stability of the construction process. The entire construction is expected to pour more than 8,800 cubic meters of concrete. The main ZOOMLION concrete equipment includes 4 70-meter pump trucks and 63-meter, 56-meter, 52-meter and other multi-meter pump truck equipment, as well as multiple 4.0 series vehicle-mounted pumps.
It is understood that the expansion project uses the third-generation nuclear power technology "Hualong One", with a single unit capacity of 1.2 million kilowatts, which is a landmark achievement of my country's independent innovation in nuclear power technology. After the project is completed, the annual power generation will exceed 20 billion kilowatt-hours, the heating area will be nearly 20 million square meters, and the population of 600,000 will benefit, providing clean, low-carbon, safe and efficient electricity and heat supply for the Shandong Peninsula.